LWCF Performance Progress Report
Lake George Regional Park Project - March 2026
Existing Recreation Hall Renovation
Roof Renovations
- Doubled up rafters and added steel rod supports to bring roof to code and snow load capacity, completed June 2024
- Existing porch roof joists and posts replaced, completed, June 2023
- Insulation and new tongue and groove ceiling installed, June 2025
- Exterior roof (south side) – new Ice And Water Shield and new shingles installed, June 2025
- Exterior roof (north side) – work to coincide with Recreation Hall Addition, construction date TBD
- Covered outdoor overhang “new porch”, completed June 2025
- Interior floor sealant or paint, completion date TBD
- Roughly 75% complete overall
Existing Building and Porch Flooring
- Interior building subfloor (conduit, pipes, and soil replacement), completed June 2023
- Interior building new concrete floor, completed June 2023
- Exterior existing porch demolition and new base construction, completed June 2023
- Exterior existing porch new concrete floor, completed June 2024
- Exterior new porch subfloor (conduit, pipes) and concrete floor work, completed May 2024
- Complete
Installing Safety Features
- New doors installed – ADA compliant access, completed June 2024 (final landscaping required for full ADA access compliance)
- Push-bar door hardware to be installed, summer 2026
- Electrical wiring per electrical permit 90% in place, wiring for fire alarm system and fire alarm system will complete, Spring 2026
- Landscaping won’t commence until all major building and road construction is complete – completion date TBD.
- Roughly 85% complete
Recreation Hall Addition (restroom facilities)
- Restrooms, utility room (for mechanical, plumbing, and heating), storage room, and concession space, not yet started. Construction date TBD
- Subsoil, sub-ground utilities, new concrete slab, landscaping, septic system construction, summer 2026
Performing General Maintenance
Ongoing as needed
Road and Site Work
- New road with tiered parking and handicap spaces & Site Work
- Major trees removed, completed Spring 2024
- 40% of road cut and Level D gravel installed, June 2024
- Some storm water systems installed, June 2024
- Catch basins, retention pond construction and other stormwater mitigation features to be constructed at a time TBD.
- Road completion date - Summer 2027
- Overall roughly 35% complete
Lakeside Cabin
- Rear doorway entrance – ADA compliant installed. ADA compliant gravel pathway to rear cabin entrance in progress. Trees removed, pathway cut out and level D gravel installed, June 2024
- Four-room floor plan revised to 2 room floor plan, and construction per plan completed, June 2024
- All electrical wiring and boxes installed to code, completed June 2024
- New windows and doors installed, June 2024
- Cabins complete except for ADA rear cabin access ramp
Park Signage
Signs will be addressed once construction is complete
Recreation Courts
Outdoor recreation courts will be installed, construction date TBD
Updated 12/24/2024